πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· WEST

Onshore wind project 2014-G1

Onshore wind project 2014-G1 is a 6.4 MW onshore wind request built and operating in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusOperating
  1. PlanningQueued Dec 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
2014-G1
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Medicine Bow
Technology
Wind: 6.4 MW
Total requested
6.4 MW
Study phase
In Service
Queue status
Operational
Entered queue
17 December 2013
Proposed online date
December 2013

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem