BATTERY STORAGE Β· SPP

Battery storage project GEN-2022-103, Christian County

Battery storage project GEN-2022-103, Christian County is a 75.0 MW battery storage request withdrawn in the SPP interconnection queue, in Christian County, Missouri, connecting to EDE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2023 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-103
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
EDE
Connection point (POI)
Ozark South 161kV
Location
Christian County, Missouri
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 January 2023
Proposed online date
January 2027
Withdrawn
March 2025

Location

Marker shows the centre of Christian County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem