CT-LI AC Tie-line

CT-LI AC Tie-line is a 600 MW other request withdrawn in the NYISO interconnection queue, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 1999 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
AEP Resources Service Corp.
Connection point (POI)
Shoreham, Long Island
Location
New York
Technology
Other: 600 MW
Total requested
600 MW
Queue status
Withdrawn
Entered queue
13 April 1999

Location

No county location in the queue data.

Power plants in New York Β· Transmission lines in New York