United States βΊ Grid βΊ Interconnection queues βΊ Missouri
SOLAR Β· SPPSolar project GEN-2018-038, Ray County
Solar project GEN-2018-038, Ray County is a 203 MW solar request withdrawn in the SPP interconnection queue, in Ray County, Missouri, connecting to GMO.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2018 (completed)
- Withdrawn / abandonedAug 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2024 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2018-038
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- GMO
- Connection point (POI)
- Sibley 345kV substation
- Location
- Ray County, Missouri
- Technology
- Solar: 203 MW
- Total requested
- 203 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 29 May 2018
- Proposed online date
- December 2024
- Came online
- December 2024
- Withdrawn
- August 2022
Location
Marker shows the centre of Ray County; the queue data does not give exact sites.
Other requests in Ray County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem