United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTHidalgo & Starr Wind
Hidalgo & Starr Wind is a 250 MW onshore wind request built and operating in the ERCOT interconnection queue.
Request details
- Queue ID
- 16INR0024
- Grid region
- ERCOT (Texas)
- Developer
- EDP Renewables
- Connection point (POI)
- New Pomelo Station on the Del Sol - North Edinburg 345 kV Line
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 24 March 2015
- Agreement signed
- 17 July 2015
- Proposed online date
- December 2019
- Came online
- December 2016
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem