United States › Grid › Interconnection queues
SOLAR + STORAGE · WESTSolar + storage project 2025-G1
Solar + storage project 2025-G1 is a 250 MW solar + storage request in interconnection study in the West interconnection queue, connecting to WAPA Rocky Mountain Region.
Queue statusIn planning
- PlanningQueued Jan 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 2025-G1
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA Rocky Mountain Region
- Connection point (POI)
- Ault 345 kV station
- Technology
- Solar: 250 MW · Battery
- Total requested
- 250 MW
- Study phase
- In Progress
- Queue status
- Active
- Entered queue
- 14 January 2024
- Proposed online date
- January 2028
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem