ONSHORE WIND Β· ERCOT

Horse Hollow 1

Horse Hollow 1 is a 220 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Oct 2004 (completed)
  2. ConsentedMay 2005 (completed)
  3. Construction (completed)
  4. OperatingTarget Jun 2005 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
05INR0018b
Grid region
ERCOT (Texas)
Developer
FPL Energy
Connection point (POI)
HHG_HHOLLOW134.500
Technology
Wind: 220 MW
Total requested
220 MW
Study phase
IA
Queue status
Operational
Entered queue
18 October 2004
Agreement signed
10 May 2005
Proposed online date
June 2005

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem