ONSHORE WIND · ERCOT

Grandview Phase I (Conway Windfarm)

Grandview Phase I (Conway Windfarm) is a 211 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Mar 2009 (completed)
  2. ConsentedOct 2012 (completed)
  3. Construction (completed)
  4. OperatingDec 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
13INR0005a
Grid region
ERCOT (Texas)
Developer
Eon Climate & Renewables
Connection point (POI)
Alibates (79500)
Technology
Wind: 211 MW
Total requested
211 MW
Study phase
IA
Queue status
Operational
Entered queue
26 March 2009
Agreement signed
24 October 2012
Proposed online date
December 2014
Came online
December 2014

Location

No county location in the queue data.

Power plants in · Transmission lines in