Surplus; J1842

Surplus; J1842 is a 50.4 MW other request withdrawn in the MISO interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
S1037
Grid region
MISO (Midcontinent)
Technology
Solar: 50.4 MW Β· Other
Total requested
50.4 MW
Queue status
Withdrawn
Entered queue
26 October 2022
Withdrawn
March 2023

Location

No county location in the queue data.