United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
BATTERY STORAGE Β· SOUTHEASTBattery storage project LGE-GIS-2021-023, Fayette County
Battery storage project LGE-GIS-2021-023, Fayette County is a 200 MW battery storage request withdrawn in the Southeast interconnection queue, in Fayette County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2021 (completed)
- Withdrawn / abandonedJan 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- LGE-GIS-2021-023
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Primary: West Lexington 345 kV; Alternate: West Lexington-Brown North 345 kV
- Location
- Fayette County, Kentucky
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 5 October 2021
- Proposed online date
- September 2024
- Withdrawn
- January 2023
Location
Marker shows the centre of Fayette County; the queue data does not give exact sites.
Other requests in Fayette County
- Grassy PlainsSolar Β· 40.0 MW Β· agreement signed
- Solar project AH1-004, Fayette CountySolar Β· 40.0 MW Β· in study
- Battery storage project AE2-338, Fayette CountyBattery storage Β· 81.2 MW Β· withdrawn
- Solar project AF1-127, Fayette CountySolar Β· 80.0 MW Β· withdrawn
- Solar project LGE-GIS-2019-022, Fayette CountySolar Β· 75.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem