United States βΊ Grid βΊ Interconnection queues βΊ Michigan
ONSHORE WIND Β· MISOOnshore wind project G799, Houghton County
Onshore wind project G799, Houghton County is a 120 MW onshore wind request withdrawn in the MISO interconnection queue, in Houghton County, Michigan.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2007 (completed)
- Withdrawn / abandonedJun 2008 (project stopped here)
- ConsentedJun 2008 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G799
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Atlantic 69kV Substation
- Location
- Houghton County, Michigan
- Technology
- Wind: 120 MW
- Total requested
- 120 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 14 May 2007
- Agreement signed
- 2 June 2008
- Proposed online date
- September 2009
- Withdrawn
- June 2008
Location
Marker shows the centre of Houghton County; the queue data does not give exact sites.
Other requests in Houghton County
- Solar + storage project J3649, Houghton CountySolar + storage Β· 200 MW Β· withdrawn
- Solar project J1823, Houghton CountySolar Β· 62.5 MW Β· withdrawn
- Solar project J1809, Houghton CountySolar Β· 62.5 MW Β· withdrawn
- Onshore wind project J1244, Houghton CountyOnshore wind Β· 38.4 MW Β· withdrawn
- Solar project J1792, Houghton CountySolar Β· 22.5 MW Β· withdrawn
- Onshore wind project J1817, Houghton CountyOnshore wind Β· 20.0 MW Β· withdrawn
- Other project J543, Houghton CountyOther Β· 19.5 MW Β· withdrawn
- Onshore wind project J1803, Houghton CountyOnshore wind Β· 1.6 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem