United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR Β· MISO

Solar project J3632, Cleveland County

Solar project J3632, Cleveland County is a 85.0 MW solar request withdrawn in the MISO interconnection queue, in Cleveland County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3632
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
TEXAS EASTERN P.S. G SS - FORDYCE ORIENT SS 115.0kV
Location
Cleveland County, Arkansas
Technology
Solar: 85.0 MW
Total requested
85.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
17 April 2024
Proposed online date
July 2028
Withdrawn
December 2025

Location

Marker shows the centre of Cleveland County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Cleveland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem