πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

Altamira Solar

Altamira Solar is a 151 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0183
Grid region
ERCOT (Texas)
Developer
J&R Power DevCo, LLC
Connection point (POI)
8985 San Ygnacio 138 kV Substation _x000D_
Technology
Solar: 151 MW
Total requested
151 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
20 January 2022
Proposed online date
March 2028

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem