BATTERY STORAGE Β· ERCOT

Elizabeth Battery

Elizabeth Battery is a 50.0 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19INR0010
Grid region
ERCOT (Texas)
Developer
Exelon
Connection point (POI)
King 138kV (40911 or 40912)
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
22 July 2016
Proposed online date
December 2019

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem