United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
SOLAR + STORAGE Β· PJMSolar + storage project AF1-089, Henry County
Solar + storage project AF1-089, Henry County is a 70.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Henry County, Kentucky, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2019 (completed)
- Withdrawn / abandonedFeb 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF1-089
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- New Castle 69 kV
- Location
- Henry County, Kentucky
- Technology
- Solar: 70.0 MW Β· Battery
- Total requested
- 70.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 30 August 2019
- Proposed online date
- June 2022
- Withdrawn
- February 2020
Location
Marker shows the centre of Henry County; the queue data does not give exact sites.
Other requests in Henry County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem