WIND + STORAGE Β· MISO

Surplus; Three Waters Wind

Surplus; Three Waters Wind is a 200 MW wind + storage request in interconnection study in the MISO interconnection queue, connecting to ITC MIDWEST.

Queue statusIn planning
  1. PlanningQueued Jan 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1013
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Lakefield Junction 345kV
Technology
Wind: 200 MW Β· Other
Total requested
200 MW
Queue status
Active
Entered queue
26 January 2022
Proposed online date
June 2026

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem