SOLAR Β· ERCOT

Pecos Solar II

Pecos Solar II is a 102 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2015 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
16INR0096
Grid region
ERCOT (Texas)
Developer
Duke Energy
Connection point (POI)
Rio Pecos 138kV (6601)
Technology
Solar: 102 MW
Total requested
102 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
16 March 2015
Proposed online date
December 2017

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem