United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project G643, Mitchell County
Onshore wind project G643, Mitchell County is a 20.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Mitchell County, Iowa.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2006 (completed)
- Withdrawn / abandonedNov 2010 (project stopped here)
- ConsentedNov 2010 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G643
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Osage Switch Station (69 kV)
- Location
- Mitchell County, Iowa
- Technology
- Wind: 20.0 MW
- Total requested
- 20.0 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 25 May 2006
- Agreement signed
- 30 November 2010
- Proposed online date
- December 2007
- Withdrawn
- November 2010
Location
Marker shows the centre of Mitchell County; the queue data does not give exact sites.
Other requests in Mitchell County
- Surplus; J449Battery storage Β· 202 MW Β· in study
- Onshore wind project J3702, Mitchell CountyOnshore wind Β· 180 MW Β· in study
- Onshore wind project J449, Mitchell CountyOnshore wind Β· 202 MW Β· built
- Onshore wind project G965, Mitchell CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project G964, Mitchell CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project J448, Mitchell CountyOnshore wind Β· 202 MW Β· withdrawn
- Onshore wind project G963, Mitchell CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project G962, Mitchell CountyOnshore wind Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem