United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTWild Horse Wind Farm 1
Wild Horse Wind Farm 1 is a 60.0 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2002 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedJul 2006 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 03INR0030a
- Grid region
- ERCOT (Texas)
- Developer
- Wild Horse Wind Farm I, LLC
- Technology
- Wind: 60.0 MW
- Total requested
- 60.0 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 29 July 2002
- Agreement signed
- 26 July 2006
- Proposed online date
- December 2050
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem