United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTMoore Wind 1
Moore Wind 1 is a 149 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedJul 2012 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 11INR0050
- Grid region
- ERCOT (Texas)
- Developer
- Moore Wind Power, LLC
- Connection point (POI)
- Cottonwood (59904)
- Technology
- Wind: 149 MW
- Total requested
- 149 MW
- Study phase
- IA
- Queue status
- Withdrawn
- Entered queue
- 20 November 2008
- Agreement signed
- 12 July 2012
- Proposed online date
- June 2015
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem