United States › Grid › Interconnection queues › Arkansas
SOLAR · MISOSolar project J907, Monroe County
Solar project J907, Monroe County is a 200 MW solar request built and operating in the MISO interconnection queue, in Monroe County, Arkansas, connecting to Entergy.
Request details
- Queue ID
- J907
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy
- Connection point (POI)
- Brinkley East - Aubrey 230 kV Line
- Location
- Monroe County, Arkansas
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 16 June 2017
- Agreement signed
- 24 March 2020
- Proposed online date
- June 2022
- Came online
- June 2022
- Withdrawn
- August 2025
Location
Marker shows the centre of Monroe County; the queue data does not give exact sites.
Other requests in Monroe County
- Solar project J1434, Monroe CountySolar · 100 MW · built
- Solar project J3540, Monroe CountySolar · 400 MW · withdrawn
- Solar project J3127, Monroe CountySolar · 160 MW · withdrawn
- Solar + storage project J2184, Monroe CountySolar + storage · 100 MW · withdrawn
- Solar project J2141, Monroe CountySolar · 100 MW · withdrawn
- Solar project J3034, Monroe CountySolar · 100 MW · withdrawn
- Solar project J1280, Monroe CountySolar · 100 MW · withdrawn
- Solar project J1261, Monroe CountySolar · 90.0 MW · withdrawn
- Solar project J2637, Monroe CountySolar · 64.5 MW · withdrawn
- Battery storage project J924, Monroe CountyBattery storage · 50.0 MW · withdrawn
- Solar project J1789, Monroe CountySolar · 6.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem