SOLAR · SOUTHEASTCane Creek Solar
Cane Creek Solar is a 78.5 MW solar request built and operating in the Southeast interconnection queue, in Clarke County, Mississippi, connecting to Southern Company.
Request details
- Queue ID
- MPCQF-451
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Location
- Clarke County, Mississippi
- Technology
- Solar: 78.5 MW
- Total requested
- 78.5 MW
- Study phase
- Operational
- Queue status
- Operational
- Agreement signed
- 19 November 2021
- Came online
- April 2024
Location
Marker shows the centre of Clarke County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Clarke County
- Gas project IC-012, Clarke CountyGas · 640 MW · withdrawn
- Solar project IC-871, Clarke CountySolar · 200 MW · withdrawn
- Solar project IC-961, Clarke CountySolar · 200 MW · withdrawn
- Solar project IC-872, Clarke CountySolar · 200 MW · withdrawn
- Solar project IC-956, Clarke CountySolar · 200 MW · withdrawn
- Other project IC-245, Clarke CountyOther · 100 MW · withdrawn
- Solar project IC-576, Clarke CountySolar · 80.0 MW · withdrawn
- Solar project IC-451, Clarke CountySolar · 78.5 MW · withdrawn
- Solar project 25-IC-AG, Clarke CountySolar · 74.9 MW · withdrawn
- Solar project IC-264, Clarke CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem