Jack County 2

Jack County 2 is a 565 MW gas request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Dec 2006 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Jun 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
10INR0010
Grid region
ERCOT (Texas)
Developer
Brazos Electric Cooperative
Connection point (POI)
JCKCNTY2_CT318.000
Technology
Gas: 565 MW
Total requested
565 MW
Study phase
FIS Complete
Queue status
Operational
Entered queue
5 December 2006
Proposed online date
June 2011

Location

No county location in the queue data.

Power plants in Β· Transmission lines in