ONSHORE WIND Β· ERCOT

Goat Wind - phase 2

Goat Wind - phase 2 is a 70.0 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Jan 2006 (completed)
  2. ConsentedNov 2006 (completed)
  3. Construction (completed)
  4. OperatingTarget Feb 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
07INR0028b
Grid region
ERCOT (Texas)
Developer
Goat Wind, LP
Connection point (POI)
GOA_GOATWIND34.500
Technology
Wind: 70.0 MW
Total requested
70.0 MW
Study phase
IA
Queue status
Operational
Entered queue
30 January 2006
Agreement signed
28 November 2006
Proposed online date
February 2008

Location

No county location in the queue data.

Power plants in Β· Transmission lines in