United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Other interconnection queue in the USA (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4382 MW
Active in queue382 MW4 requests
Agreement signed82.0 MW3 requests
Withdrawn244,375 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project 62, Pima County
Other
300 MWIn study Pima, AZWest Sep 2018target 2023
Other project 66, Stevens County
Other
71.0 MWAgreement signed Stevens, WAWest Jul 2018target 2026
Other project J963, Cedar County
Other
9.0 MWAgreement signed Cedar, IAMISO Mar 2018target 2017
Other project J953, Johnson County
Other
2.0 MWAgreement signed Johnson, IAMISO Mar 2018target 2006

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)