United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Wisconsin (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51,312 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn51,312 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J294, Brown County
Gas
588 MWWithdrawn / abandoned Brown, WIMISO Sep 2013target 2020
Gas project J293, Outagamie County
Gas
496 MWWithdrawn / abandoned Outagamie, WIMISO Sep 2013target 2016
Onshore wind project J314, Columbia County
Onshore wind
101 MWWithdrawn / abandoned Columbia, WIMISO Nov 2013target 2017
Onshore wind project J315, Rock County
Onshore wind
101 MWWithdrawn / abandoned Rock, WIMISO Nov 2013target 2017
Coal project J269, Columbia County
Coal
26.0 MWWithdrawn / abandoned Columbia, WIMISO Jan 2013target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)