Projects with signed interconnection agreements in Wisconsin (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2451 MW
Active in queue5,600 MW33 requests
Agreement signed451 MW2 requests
Withdrawn182,087 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1513, Waupaca County
Solar
300 MWAgreement signed Waupaca, WIMISO Feb 2022target 2026
Solar project J1751, Wood County
Solar
151 MWAgreement signed Wood, WIMISO Apr 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)