United States β€Ί Grid β€Ί Interconnection queues β€Ί West Virginia

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in West Virginia (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown42,148 MW
Active in queue150 MW2 requests
Agreement signed150 MW2 requests
Withdrawn42,148 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AE2-167, Doddridge County
Gas
1,335 MWWithdrawn / abandoned Doddridge, WVPJM Mar 2019target 2023
Gas project AE2-168, Doddridge County
Gas
665 MWWithdrawn / abandoned Doddridge, WVPJM Mar 2019target 2023
Gas project AF1-065, Brooke County
Gas
100 MWWithdrawn / abandoned Brooke, WVPJM Jul 2019target 2022
Hydro project AE2-159, Fayette County
Hydro
48.0 MWWithdrawn / abandoned Fayette, WVPJM Mar 2019target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)