United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

OCTARY USA Β· INTERCONNECTION QUEUES

Hydro interconnection queue in Washington

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2555 MW
Active in queue555 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn14395 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Hydro project G0490, Douglas County
Hydro
345 MWIn study Douglas, WAWest Jul 2013target 2022
Hydro project G0535, Walla Walla County
Hydro
210 MWIn study Walla Walla, WAWest May 2016target 2031

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)