United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Virginia (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8230 MW
Active in queue6,737 MW37 requests
Agreement signed3,049 MW27 requests
Withdrawn617,607 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Greensville Power Station
Gas
75.0 MWOperating Greensville, VAPJM Mar 20192023
Bartonsville Energy Facility
Solar
70.0 MWOperating Frederick, VAPJM Mar 20192024
Watlington Solar
Solar
20.0 MWOperating Halifax, VAPJM Aug 20192023
Pleasant Hill Solar
Solar
20.0 MWOperating City Of Suffolk, VAPJM Dec 20192023
Stratford Solar Center
Solar
15.0 MWOperating City Of Suffolk, VAPJM May 20192023
Warren County Power Station
Gas
15.0 MWOperating Warren, VAPJM Mar 20192020
Bartonsville Energy Facility
Solar
10.0 MWOperating Frederick, VAPJM Oct 20192024
Hanover Solar
Solar
5.0 MWOperating Hanover, VAPJM Mar 20192020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)