United States βΊ Grid βΊ Interconnection queues βΊ Utah
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Utah (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project C1-32, Millard County Onshore wind |
456 MW | Withdrawn / abandoned |
| Solar + storage project C1-22, Iron County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project C1-47, Iron County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project C1-52, Tooele County Solar + storage |
250 MW | Withdrawn / abandoned |
| Solar + storage project C1-06, San Juan County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project C1-09, Juab County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project C1-07, San Juan County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project C1-08, Juab County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar project C1-28, Iron County Solar |
199 MW | Withdrawn / abandoned |
| Solar + storage project C1-17, Box Elder County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar + storage project C1-18, Tooele County Solar + storage |
160 MW | Withdrawn / abandoned |
| Geothermal project C1-05, Millard County Geothermal |
115 MW | Withdrawn / abandoned |
| Solar + storage project C1-30, Beaver County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C1-26, Carbon County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar project C1-33, San Juan County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project C1-56, Salt Lake County Battery storage |
49.0 MW | Withdrawn / abandoned |
| Geothermal project C1-29, Beaver County Geothermal |
40.0 MW | Withdrawn / abandoned |
| Solar + storage project C1-13, Carbon County Solar + storage |
35.0 MW | Withdrawn / abandoned |
| Solar + storage project C1-12, Carbon County Solar + storage |
25.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)