United States βΊ Grid βΊ Interconnection queues βΊ Utah
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Utah (2014 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project 614, San Juan County Onshore wind |
199 MW | Withdrawn / abandoned |
| Gas project 582, Utah County Gas Β· PacifiCorp Energy |
139 MW | Withdrawn / abandoned |
| Solar project 587, Emery County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 601, Emery County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 588, San Juan County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 610, Juab County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 591, Juab County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 574, Tooele County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 575, Salt Lake County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 602, Sevier County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 576, Salt Lake County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project 590, Juab County Solar |
50.0 MW | Withdrawn / abandoned |
| Gas project 558, Tooele County Gas |
21.0 MW | Withdrawn / abandoned |
| Solar project 595, Millard County Solar |
20.0 MW | Withdrawn / abandoned |
| Other project 637, Salt Lake County Other |
18.0 MW | Withdrawn / abandoned |
| Other project 627, Salt Lake County Other |
15.0 MW | Withdrawn / abandoned |
| Hydro project 617, Utah County Hydro |
11.5 MW | Withdrawn / abandoned |
| Solar project 622, Millard County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project 623, Millard County Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project 561, Millard County Solar |
10.0 MW | Withdrawn / abandoned |
| Gas project 619, Salt Lake County Gas |
6.3 MW | Withdrawn / abandoned |
| Solar project 584-B, Utah County Solar |
5.2 MW | Withdrawn / abandoned |
| Solar project 568, Emery County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project 569, Emery County Solar |
5.0 MW | Withdrawn / abandoned |
| Gas project 626, Salt Lake County Gas |
3.0 MW | Withdrawn / abandoned |
| Solar project 550, Millard County Solar |
3.0 MW | Withdrawn / abandoned |
| Solar project 583, Juab County Solar Β· PacifiCorp Energy |
3.0 MW | Withdrawn / abandoned |
| Solar project 584-A, Utah County Solar |
2.2 MW | Withdrawn / abandoned |
| Solar project 615, Washington County Solar |
2.0 MW | Withdrawn / abandoned |
| Solar project 628, Salt Lake County Solar |
1.0 MW | Withdrawn / abandoned |
| Solar project 596, Beaver County Solar |
1.0 MW | Withdrawn / abandoned |
| Solar project 625, Sevier County Solar Β· South Valley Sustainability Park |
1.0 MW | Withdrawn / abandoned |
| Solar project 546, Sevier County Solar |
0.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)