United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Texas (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51,797 MW
Active in queue1,797 MW5 requests
Agreement signed405 MW2 requests
Withdrawn285,821 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
FGE Texas 2 Gas
Gas Β· FGE Power
743 MWPaused / redesign Mitchell, TXERCOT Feb 2014target 2028
Halyard Wharton
Gas Β· Halyard Energy
484 MWPaused / redesign Wharton, TXERCOT Mar 2014target 2021
Nazareth Solar
Solar Β· TX Nazareth Solar, LLC
203 MWAgreement signed Castro, TXERCOT Jun 2014target 2027
Mesteno Wind
Onshore wind Β· Mesteno Windpower, LLC
202 MWAgreement signed Starr, TXERCOT Dec 2014target 2025
Hart Wind (Old POI)
Onshore wind
165 MWPaused / redesign Castro, TXERCOT Feb 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)