United States β€Ί Grid β€Ί Interconnection queues β€Ί Tennessee

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Tennessee (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5749 MW
Active in queue173 MW6 requests
Agreement signed173 MW6 requests
Withdrawn5749 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 331, Gibson County
Onshore wind
196 MWWithdrawn / abandoned Gibson, TNSoutheast Oct 2017
Gas project 311, Morgan County
Gas
192 MWWithdrawn / abandoned Morgan, TNSoutheast Mar 2017
Solar project 326, Haywood County
Solar
150 MWWithdrawn / abandoned Haywood, TNSoutheast Aug 2017
Solar project 335, Fayette County
Solar
132 MWWithdrawn / abandoned Fayette, TNSoutheast Nov 2017
Solar project 336, Haywood County
Solar
79.0 MWWithdrawn / abandoned Haywood, TNSoutheast Dec 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)