πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί South Carolina

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in South Carolina (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown271.5 MW
Active in queue172 MW3 requests
Agreement signed71.5 MW2 requests
Withdrawn254,613 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 164382, Laurens County
Solar
37.5 MWAgreement signed Laurens, SCSoutheast Mar 2020target 2026
Solar project 126066, Greenwood County
Solar
34.0 MWAgreement signed Greenwood, SCSoutheast Mar 2020target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)