United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Oregon (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown84,609 MW
Active in queue4,689 MW11 requests
Agreement signed80.0 MW3 requests
Withdrawn296,595 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project G0648, Klamath County
Solar + storage
1,400 MWIn study Klamath, ORWest May 2020target 2026
Solar + storage project G0657, Klamath County
Solar + storage
1,000 MWIn study Klamath, ORWest Sep 2020target 2027
Battery storage project G0642, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2025
Battery storage project G0643, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2024
Solar project G0651, Lake County
Solar
400 MWIn study Lake, ORWest Jul 2020target 2023
Onshore wind project G0640, Klamath County
Onshore wind
239 MWIn study Klamath, ORWest Feb 2020target 2025
Solar project G0655, Lake County
Solar
200 MWIn study Lake, ORWest Aug 2020target 2027
Solar project G0654, Lake County
Solar
170 MWIn study Lake, ORWest Aug 2020target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)