Requests shown716.3 MW
Active in queue1,138 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn515,433 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Hydro project 364, Lane County
Hydro Β· Dorena Lake, LLC
6.8 MWOperating Lane, ORWest Dec 2010target 2012
Other project 360, Morrow County
Other Β· TMF Biofuels, LLC
4.8 MWOperating Morrow, ORWest Nov 2010target 2013
Other project G0439, Lane County
Other
2.0 MWOperating Lane, ORWest Nov 2010target 2011
Other project 366, Douglas County
Other Β· Roseburg LFG Energy, LLC
1.6 MWOperating Douglas, ORWest Dec 2010target 2011
Outback
Solar Β· Outback Solar, LLC
1.0 MWOperating Lake, ORWest Aug 2010target 2010
Hydro project 355, Josephine County
Hydro Β· Mountain Energy Inc.
0.1 MWOperating Josephine, ORWest Nov 2010target 2011
Hydro project 352, Clatsop County
Hydro Β· City of Astoria
0.0 MWOperating Clatsop, ORWest Sep 2010target 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)