United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Oregon (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown91,097 MW
Active in queue23.9 GW57 requests
Agreement signed1,097 MW9 requests
Withdrawn9940.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project C2-158, Crook County
Solar + storage Β· Mormont Solar, LLC
199 MWAgreement signed Crook, ORWest May 2022target 2032
Solar + storage project C2-114, Crook County
Solar + storage Β· Tumalo Solar, LLC
199 MWAgreement signed Crook, ORWest May 2022target 2032
Battery storage project C2-178, Crook County
Battery storage Β· Oathkeeper Storage, LLC
199 MWAgreement signed Crook, ORWest May 2022target 2032
Battery storage project C2-27, Multnomah County
Battery storage Β· Troutdale Grid, LLC
100 MWAgreement signed Multnomah, ORWest Apr 2022target 2028
Solar + storage project C2-07, Crook County
Solar + storage Β· Three Springs Interconnection D LLC
80.0 MWAgreement signed Crook, ORWest Apr 2022target 2036
Solar project C2-06, Crook County
Solar Β· Gadget Solar LLC
80.0 MWAgreement signed Crook, ORWest Apr 2022target 2036
Solar + storage project C2-08, Crook County
Solar + storage Β· Under the Butte LLC
80.0 MWAgreement signed Crook, ORWest Apr 2022target 2036
Solar + storage project C2-09, Crook County
Solar + storage Β· SSEV D LLC
80.0 MWAgreement signed Crook, ORWest Apr 2022target 2036
Solar + storage project C2-175, Umatilla County
Solar + storage Β· Blue Mountain Solar, LLC
80.0 MWAgreement signed Umatilla, ORWest May 2022target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)