United States βΊ Grid βΊ Interconnection queues βΊ Oregon
OCTARY USA Β· INTERCONNECTION QUEUESProjects with signed interconnection agreements in Oregon (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project TCS-44, Crook County Solar + storage Β· Three Springs Interconnection B LLC |
80.0 MW | Agreement signed |
| Solar project QF19-081, Jefferson County Solar |
53.0 MW | Agreement signed |
| Solar + storage project TCS-45, Crook County Solar + storage Β· Three Springs Interconnection C LLC |
40.0 MW | Agreement signed |
| Solar + storage project TCS-43, Crook County Solar + storage Β· Three Springs Interconnection A LLC |
40.0 MW | Agreement signed |
| Solar project TCS-40, Benton County Solar Β· Oregon State University |
0.8 MW | Agreement signed |
| Solar project TCS-38, Benton County Solar Β· Oregon State University |
0.3 MW | Agreement signed |
| Solar project TCS-39, Benton County Solar Β· Oregon State University |
0.2 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)