Completed queue projects in Oklahoma (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6865 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn111,501 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2014-056, Canadian County
Onshore wind
250 MWOperating Canadian, OKSPP Sep 20142018
Onshore wind project GEN-2014-057, Grady County
Onshore wind
250 MWOperating Grady, OKSPP Sep 20142016
Onshore wind project GEN-2014-064, Garfield County
Onshore wind
248 MWOperating Garfield, OKSPP Sep 20142018
Onshore wind project GEN-2014-020, Grady County
Onshore wind
100 MWOperating Grady, OKSPP Jul 20142017
Onshore wind project GEN-2014-002, Dewey County
Onshore wind
10.5 MWOperating Dewey, OKSPP Feb 20142015
Onshore wind project GEN-2014-005, Caddo County
Onshore wind
5.7 MWOperating Caddo, OKSPP Feb 20142015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)