United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Oklahoma (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4634 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn101,688 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2010-001, Beaver County
Onshore wind
300 MWOperating Beaver, OKSPP Mar 20102015
Onshore wind project GEN-2010-040, Canadian County
Onshore wind
300 MWOperating Canadian, OKSPP Aug 20102012
Onshore wind project GEN-2010-011, Dewey County
Onshore wind
29.7 MWOperating Dewey, OKSPP Mar 20102012
Gas project GEN-2010-055, Tulsa County
Gas
4.5 MWOperating Tulsa, OKSPP Sep 20102013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)