πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Oklahoma (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3262 MW
Active in queue5,119 MW34 requests
Agreement signed262 MW3 requests
Withdrawn8215.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2023-GR1, Caddo County
Gas
97.5 MWAgreement signed Caddo, OKSPP Jan 20232025
Gas project GEN-2023-GR2, Oklahoma County
Gas
94.2 MWAgreement signed Oklahoma, OKSPP Feb 2023target 2026
Battery storage project GEN-2023-SR16, Woodward County
Battery storage
70.0 MWAgreement signed Woodward, OKSPP Apr 20232025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)