United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in North Dakota (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4600 MW
Active in queue600 MW4 requests
Agreement signed0.0 MW0 requests
Withdrawn164,278 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J2080, Oliver County
Onshore wind
200 MWIn study Oliver, NDMISO Aug 2021target 2024
Onshore wind project J2250, Stutsman County
Onshore wind
200 MWIn study Stutsman, NDMISO Nov 2021target 2024
Onshore wind project J2157, Morton County
Onshore wind
100 MWIn study Morton, NDMISO Aug 2021target 2025
Onshore wind project J2097, Morton County
Onshore wind
100 MWIn study Morton, NDMISO Aug 2021target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)