United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in New York (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4910 MW
Active in queue910 MW4 requests
Agreement signed0.0 MW0 requests
Withdrawn302,962 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Bull Run II Wind
Onshore wind Β· Bull Run Energy LLC
449 MWIn study Clinton, NYNYISO Dec 2015target 2028
Canisteo Wind
Onshore wind Β· Canisteo Wind Energy LLC
291 MWIn study Steuben, NYNYISO Nov 2015target 2027
Mohawk Solar
Solar Β· Mohawk Solar LLC
90.5 MWIn study Montgomery, NYNYISO Apr 2015target 2027
NYC Energy
Battery storage Β· NYC Energy LLC
79.9 MWIn study Kings, NYNYISO Dec 2015target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)