United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in New Mexico (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2512 MW
Active in queue512 MW2 requests
Agreement signed512 MW2 requests
Withdrawn142,370 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project IA-PNM-2016-02, Torrance Cty County
Onshore wind Β· Pacific Wind Development
402 MWAgreement signed Torrance Cty, NMWest May 2016target 2020
Solar project GEN-2016-121, Lea County
Solar
110 MWAgreement signed Lea, NMSPP Nov 2016target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)