Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown142,370 MW
Active in queue512 MW2 requests
Agreement signed512 MW2 requests
Withdrawn142,370 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
LA450S
Solar
450 MWWithdrawn / abandoned Luna, NMWest Sep 2016target 2019
Onshore wind project GEN-2016-076, Roosevelt County
Onshore wind
396 MWWithdrawn / abandoned Roosevelt, NMSPP Jun 2016target 2018
Onshore wind project GEN-2016-084, Lea County
Onshore wind
300 MWWithdrawn / abandoned Lea, NMSPP Jun 2016target 2019
Onshore wind project IA-PNM-2016-01, Guadalupe Cty County
Onshore wind
300 MWWithdrawn / abandoned Guadalupe Cty, NMWest May 2016target 2019
Solar project GEN-2016-169, Lea County
Solar
260 MWWithdrawn / abandoned Lea, NMSPP Nov 2016target 2018
Solar project GEN-2016-086, Roosevelt County
Solar
240 MWWithdrawn / abandoned Roosevelt, NMSPP Jun 2016target 2019
Solar project GEN-2016-080, Lea County
Solar
100 MWWithdrawn / abandoned Lea, NMSPP Jun 2016target 2019
Solar project IA-PNM-2016-04, Hidalgo County
Solar
80.0 MWWithdrawn / abandoned Hidalgo, NMWest Nov 2016target 2019
Solar project GEN-2016-085, Lea County
Solar
80.0 MWWithdrawn / abandoned Lea, NMSPP Jun 2016target 2019
Solar project GEN-2016-171, Lea County
Solar
64.0 MWWithdrawn / abandoned Lea, NMSPP Nov 2016target 2020
Solar project IA-PNM-2016-03, Valencia County
Solar
49.0 MWWithdrawn / abandoned Valencia, NMWest Nov 2016target 2019
Solar project GEN-2016-069, Chaves County
Solar
31.4 MWWithdrawn / abandoned Chaves, NMSPP Mar 2016target 2018
Solar project SGI-PNM-2016-03, Sandoval County
Solar
10.0 MWWithdrawn / abandoned Sandoval, NMWest Nov 2016target 2019
Solar project SGI-PNM-2016-02, Sandoval County
Solar
10.0 MWWithdrawn / abandoned Sandoval, NMWest Nov 2016target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)