United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in New Mexico (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown191,796 MW
Active in queue109 MW2 requests
Agreement signed80.0 MW1 requests
Withdrawn191,796 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

19 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2014-008, Lea County
Onshore wind
300 MWWithdrawn / abandoned Lea, NMSPP Mar 2014target 2018
Other project IA-PNM-2014-01, Guadalupe Cty County
Other
300 MWWithdrawn / abandoned Guadalupe Cty, NMWest Feb 2014target 2015
Solar project GEN-2014-030, Lea County
Solar
150 MWWithdrawn / abandoned Lea, NMSPP Sep 2014target 2016
Solar project GEN-2014-046, Chaves County
Solar
125 MWWithdrawn / abandoned Chaves, NMSPP Sep 2014target 2016
Onshore wind project GEN-2014-063, Chaves County
Onshore wind
120 MWWithdrawn / abandoned Chaves, NMSPP Sep 2014target 2016
Solar project GEN-2014-070, Lea County
Solar
113 MWWithdrawn / abandoned Lea, NMSPP Sep 2014target 2016
Solar project GEN-2014-048, Chaves County
Solar
110 MWWithdrawn / abandoned Chaves, NMSPP Sep 2014target 2016
Solar project GEN-2014-024, Lea County
Solar
100 MWWithdrawn / abandoned Lea, NMSPP Sep 2014target 2016
Solar project GEN-2014-065, Lea County
Solar
99.0 MWWithdrawn / abandoned Lea, NMSPP Sep 2014target 2016
DS90S
Solar
90.0 MWWithdrawn / abandoned Dona Ana, NMWest Oct 2014target 2016
Solar project GEN-2014-069, Eddy County
Solar
90.0 MWWithdrawn / abandoned Eddy, NMSPP Sep 2014target 2016
Palace Solar
Solar
49.0 MWWithdrawn / abandoned Valencia Cty, NMWest Nov 2014target 2016
Solar project IA-PNM-2014-08, Valencia Cty County
Solar
49.0 MWWithdrawn / abandoned Valencia Cty, NMWest Nov 2014target 2016
Solar project GEN-2014-047, Roosevelt County
Solar
40.0 MWWithdrawn / abandoned Roosevelt, NMSPP Sep 20142017
Solar project GEN-2014-066, Quay County
Solar
30.0 MWWithdrawn / abandoned Quay, NMSPP Sep 2014target 2016
Solar project SGI-PNM-2014-10, Bernalillo County
Solar
10.0 MWWithdrawn / abandoned Bernalillo, NMWest Nov 2014target 2015
Solar project SGI-PNM-2014-02, Santa Fe County
Solar
10.0 MWWithdrawn / abandoned Santa Fe, NMWest Jan 2014target 2015
Solar project SGI-PNM-2014-07
Solar
6.0 MWWithdrawn / abandoned NMWest Aug 2014target 2015
Solar project SGI-PNM-2014-04, Santa Fe County
Solar
5.0 MWWithdrawn / abandoned Santa Fe, NMWest Jun 2014target 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)