Completed queue projects in New Mexico (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1105 MW
Active in queue2,724 MW13 requests
Agreement signed2,054 MW8 requests
Withdrawn152,748 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Duran Mesa
Onshore wind
105 MWOperating Torrence, NMWest Aug 2020target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)