Completed queue projects in New Mexico (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5165 MW
Active in queue29.0 MW1 requests
Agreement signed29.0 MW1 requests
Withdrawn121,415 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
NMRD Data Center II
Solar
60.0 MWOperating Torrance, NMWest Aug 2015
NMRD Data Center III
Solar
60.0 MWOperating Sandoval Cty, NMWest Aug 2015target 2020
Solar project TI-15-0227, Luna County
Solar
25.0 MWOperating Luna, NMWest Feb 20152016
Solar project SGI-PNM-2015-03, San Miguel County
Solar
10.0 MWOperating San Miguel, NMWest Jun 2015
Solar project SGI-PNM-2015-04, Bernalillo County
Solar
10.0 MWOperating Bernalillo, NMWest Jun 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)