United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in New Jersey (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown659.0 MW
Active in queue563 MW13 requests
Agreement signed546 MW11 requests
Withdrawn352,924 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Mount Olive Solar Farm
Solar
19.8 MWOperating Morris, NJPJM Mar 20202023
Foul Rift Solar Farm
Solar
15.4 MWOperating Warren, NJPJM Oct 20202025
Holland Solar Farm
Solar
8.8 MWOperating Hunterdon, NJPJM Mar 20202022
FLR Florence Landfill
Solar
5.0 MWOperating Burlington, NJPJM Mar 20202022
Princeton University Generating Facility
Other
5.0 MWOperating Mercer, NJPJM Mar 20202022
Rutgers Generation
Gas
5.0 MWOperating Essex, NJPJM Sep 20202024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)